IMPSA begins modernization of Macagua and Tocoma to restore 672 MW within two years

Economy Featured Infrastructure Oil & Energy

The Daily Journal – Argentine-American company IMPSA has formally launched a modernization project at the Macagua and Tocoma hydroelectric power plants in Venezuela’s Bolívar state, aiming to restore electricity generation capacity in a system facing serious deficiencies.

According to information the company released, the first phase of the plan aims to restore 160 megawatts (MW) at Macagua by rehabilitating generating units 5 and 6, a milestone the company expects to achieve within 90 days. The overall project, which covers both power plants, seeks to restore a total of 672 MW over the next two years.

The project breakdown calls for rehabilitating units 4, 5, and 6 at Macagua to restore 240 MW, while work on units 1 and 2 at Tocoma will contribute an additional 432 MW. The company said these efforts are part of a master plan to achieve a combined installed capacity of up to 2,640 MW at both facilities in the long term.

The parties signed the corresponding contract last August at Miraflores Palace, in the presence of Venezuela’s Acting President Delcy Rodríguez and electricity sector officials. At the time, the Venezuelan government linked the agreement to the need to address electricity demand, which had reached its highest level in eight years at 15,726 MW.

Background

Venezuela’s electricity system relies heavily on the Lower Caroní hydroelectric complex, which includes Guri, Caruachi, Macagua, and Tocoma. For years, the system has operated below installed capacity because of insufficient maintenance and stalled infrastructure projects.

Construction of Tocoma began in 2007 but halted after workers completed more than 87% of the project. The facility has yet to achieve full commercial operation.

Energy sector experts have warned that restoring specific generating units at Macagua and Tocoma, while providing some immediate relief, will not resolve the system’s structural deficiencies. These challenges also include deteriorating thermal power plants and an overloaded transmission network.

Meanwhile, the U.S. Embassy in Caracas has placed the project within the three-phase plan that the Donald Trump administration has promoted for Venezuela, encompassing stabilization, economic recovery, and political transition.